After more than a month, it is done. And it’s raining.
~kp~
July 5, 2009
June 14, 2009
After a week in which we endured downtime having run out of wood, deck screws, and cable hardware, and in which our area saw a wave of thunderstorms packing winds in excess of seventy miles an hour pelt us with anywhere between six and eight inches of rain in less than a twenty-four hour period beginning 7 p.m. Wednesday evening, construction on the deck is finally finished.
Now it’s a matter of letting the wood dry out sufficiently enough in order for us to stain it.
The new deck clocks in almost exactly at 275 square feet, and makes us feel like we will really be able to spread out when everything is back in order.
Special thanks go out to our friend Mark, not only for providing the structural design, but for lending his expertise and sharing his wealth of knowledge over the course of this project.

One of my favorite features: rows of 2x2 cedar serve as deck skirting, which looks great and denies our dog (and other critters) access underneath the deck.

This shot shows the deck cantilevered out over the edge of the flagstone wall. The stairway handrail (top right) was a sorely needed addition; the flagstone can be very slick when wet.
~kp~
June 7, 2009
A little shorter workday Saturday, but we still made good progress. The first seven rows or so of decking material are in place, and our three outside handrail posts, which until now had only been held in place by a couple of temporary screws, are permanently affixed with a pair of six-inch bolts driven through them. They aren’t going anywhere. Trust me.
And the transformer for our sprinkler control box, which had been laying on the damp ground underneath the old deck for God only knows how many years (who made that wildly unstable decision?), is now safe, hidden, and secure in an external outlet box mounted to one of our new joists.
With my vacation over and my return to work imminent, my contributions on the deck are mostly over until sanding, staining and sealing. I’d anticipate that all the construction will be wrapped up within the next two or three days by our handyman extraordinaire.

This mess of spliced wiring and the transformer for our sprinkler system was uncovered during demolition, laying in the damp soil below our old deck.

Not anymore. For about twelve bucks a weather resistant junction box mounted to one of the new deck joists has us breathing easier.

Shown here is the ledger bolted to the foundation of the house just below the sill of the sliding glass doors. With much of the weight of the deck now transferred to the house via ten 2x8 joists, we saved ourselves the trouble of digging and pouring concrete for four more posts. Metal flashing and liberal use of caulk should keep water away.

This shot shows the two center beams (bottom), one of ten joists hung over it, and the decking layer on top. One of our six handrail posts is at the top right.
~kp~
June 5, 2009
Another long but solid day of progress on Friday. All ten of our joists are installed, our hand rail posts are in, level, and at the proper height, and the funky corner around the top of the flagstone steps is framed. We are essentially ready to begin putting down decking material.
~kp~
June 5, 2009
A productive day Thursday, nearly eleven hours from start to finish, but for the first time our efforts are taking shape, and we can now glimpse what will be when this project is finished.
The day began by attaching seven cedar posts, then installing four beams that span the width of the deck. It took us a while to get everything square, but we are now within about 3/16″ of being exactly square, not bad considering the foundation to which our ledger is attached isn’t true either, and looks like it bowed in a couple of places when it was poured thirty-eight years ago.

View 3 - Day 4. With the deck now cantilevered out over the flagstone wall, it feels like it will be much larger than the old one.
~kp~
June 4, 2009
Yesterday was almost a total loss, as we waited for the 2nd straight day for our lumber to arrive. It finally showed up around four o’clock in the afternoon. Not much time for anything other than to haul it into the garage, and, for a few long pieces, the house, as evidenced in the photos below.
Tuesday was pretty humbling, as we endured what was pretty much a physical beating. We spent the day hammer-drilling into the foundation of our house to attach the ledger (so the house will now bear much of the weight of the deck, eliminating the need for four additional posts), drilling the soil for our post holes, moving dirt so the soil under the deck will drain properly, hauling 60-pound bags of concrete outside, and mixing and shoveling it into our seven post holes.
As a result, three days in and about all we have to show for our efforts is the site layout, our ledger attached, and our post holes dug and poured with concrete, J-bolts at the ready.
The house, by the way, smells amazing with all that cedar.

Day 3 - A few of the longest pieces, as long as twenty feet, had to be stashed in the front hallway overnight.
~kp~
June 3, 2009
It’s now June, and our remodeling efforts head outside to tackle the last large project for a while: rebuilding the old, rotted deck we inherited with a new one that will be better looking, uses better materials, and is better designed to withstand the effects of mother nature.
The main problem with the old deck, other than the fact that it was probably at least three decades old, was that although the posts were in concrete, the concrete was several inches underground. As a result, nearly all of the 19 wood posts were constantly exposed to moisture in the soil, which is why some them broke off easily during demolition. A couple of them were rotted up to 90% through at the soil level.
I didn’t bother taking any photos of the demolition, mostly because it was an unholy mess. Suffice to say that it took two full days of work over the course of two weekends, along with the much appreciated borrowing of pickup trucks from two friends to haul away three loads of debris.
For this project we’ve enlisted the help of a handyman friend who provided a nifty design along with his expertise. I am merely serving as his sous chef while I take a week of vacation to help out. A couple of days in, one thing is apparent: this would be nearly an impossible job for one person to do alone, no matter the experience. There is just too much lifting, positioning, mixing and pouring of concrete and so on for one person to do without nearly dropping dead.
The basic layout of the new deck is not much different than the old one. Handrails will replace the U-shaped bench that surrounded most of the perimeter facing the yard. And the old flagstone at the deck level, which was unsightly and a ridiculous trip hazard, has been removed.
The new deck will have a more contemporary look to complement the mid-century modern design of the townhouse. And we’ve chosen cedar to replace the untreated lumber of the old deck, which should be much more durable and is not as prone to warping as pressure-treated wood.
What you see below are photos of the old deck and a nice, but organized pile of dirt after a day and a half of work, taken during a rain delay. I’ll try to post updates at least every other day from here on out. Provided I have the energy left to pick up a camera, that is.

View 1 - Day 2. Taken during an hour-long rain delay the morning of Day 2. Note at this point five of seven new post holes are dug and ready for concrete.
~kp~